Belmont Station Elementary, 20235 Nightwatch St., Ashburn. Virginia DEQ's records show 6 data centers within 2 miles: 2 planned, 4 operating. 0 within 1 mile.
12 filings (land-use applications and site plans) that mention a data center, from Loudoun County records; 9 still in county review. Filings come before any DEQ air permit, so some of these may not be on DEQ's records yet.
-
BELMONT INNOVATION CAMPUS BUILDINGS 1, 2 and 5 - CONSTRUCTION OF 3 DATA CENTER BUILDINGS WITH ALL ASSOCIATED ACCESS & UTILITIES.
-
Project proposing Data Center buildings 1-3 of the Twin Creeks site with associated landscaping and infrastructure.
-
(APPROVED) COCHRAN MILL ROAD : REQUEST APPROVAL OF A SITE PLAN (STPL) FOR THE REDEVELOPMENT OF MULTIPLE MATERIAL MANUFACTURING PLANTS AND NEW DEVELOPMENT CONSISTING OF THREE (3) DATA CENTERS, TWO (2) WAREHOUSES AND…
-
COCHRAN TECH: See LEGI-2024-0037 for all timelines, document, and updates. A Special Exception to allow a data center development on moderately steep slopes in the IP Zoning District.
-
COCHRAN TECH: See LEGI-2024-0037 for all timelines, document, and updates. A Special Exception to allow data center use in the IP Zoning District.
-
COCHRAN TECH: A Zoning Map Amendment to rezone an approximately 17.52-acre property from the Joint Land Management Area - 3 (JLMA-3) Zoning District to the Industrial Park (IP) Zoning District to allow IP uses. A…
-
TWIN CREEKS DATA CENTERS: Site containing two data center buildings with associated infrastructure and landscaping. (REVISION OF APPROVED PLAN STPL-2022-0040)
-
PROJECT ASPEN SPAM: This is a revision to EPLAN-2023-0128 to adjust the Mechanical Yard (MYD) per new specifications provided by the Owner. The revision does not change the Data Center, Electrical Yard or any of the…
-
PROJECT ASPEN: FAST TRACK Site Plan is for the Phase 3 extension of the existing Data Center complex with associated support facilities.
-
SAMUELS MILL ASSEMBLAGE: 2-story data center and associated infrastructure.
-
(Conditional Approval) CYRUSONE BROADLANDS DATA CENTER : REQUESTED APPROVAL OF A SITE PLAN (STPL) FOR A DATA CENTER DEVELOPMENTON APPROXIMATELY FIFTY EIGHT (58) ACRES, DEVELOPMENT CONSISTS OF APPROXIMATELY SEVEN HUNDRED…
-
(Conditional Approval 08-05-24) TELOS DATA CENTER : REQUEST APPROVAL OF A SITE PLAN (STPL) FOR THE CONSTRUCTION OF A PUBLIC DATA CENTER, IN THE PLANNED DEVELOPMENT INDUSTRIAL PARK (PDIP) ZONING DISTRICT.
Straight-line distance from the school's location (National Center for Education Statistics).
Virginia's 2026 siting law requires a sound study covering schools within 500 feet of a new high-energy
facility before a county can approve it.