Creighton's Corner Elementary, 23171 Minerva Drive, Ashburn. Virginia DEQ's records show 5 data centers within 2 miles: 1 planned, 4 operating. 0 within 1 mile.
17 filings (land-use applications and site plans) that mention a data center, from Loudoun County records; 13 still in county review. Filings come before any DEQ air permit, so some of these may not be on DEQ's records yet.
-
(Conditional Approval) BRAMBLETON SHREVEPORT SOUTH DATA CENTER : REQUEST APPROVAL OF A SITE PLAN (STPL) FOR THE CONSTRUCTION OF A TWO (2) DATA CENTERS AND SUPPORTING UTILITIES, IN THE PLANNED DEVELOPMENT INDUSTRIAL PARK…
-
(Conditional Approval) DULLES TRADE CENTER LOTS 10 & 11 : REQUEST APPROVAL OF A SITE PLAN AMENDMENT (SPAM) FOR THE CONVERTING OFBUILDING USE FROM WAREHOUSE TO DATA CENTER, IN THE (PDGI) PLANNED DEVELOPMENT GENERAL…
-
CLINTMAR DATA CENTERS: The development of vacant parcels to provide a 2-story Data Center with associated infrastructure and improvements.
-
This project proposes construction of an approximately 100,000 SF data center, parking lot and associated utilities to serve the building. The total disturbed area is 10.58 AC.
-
BRAMBLETON BUSINESS CAMPUS DATA CENTER : REQUEST APPROVAL OF A SITE PLAN (STPL) FOR THE CONSTRUCTION OF A TWO (2) DATA CENTERS AND SUPPORTING UTILITIES, IN THE PLANNED DEVELOPMENT INDUSTRIAL PARK (PDIP) AND THE PLANNED…
-
ALLEGRO NORTH CAMPUS - BLDG 2B-2E: The Site Plan is for Buildings 2B-2E of the North Campus of a data center complex with associated support facilities.
-
CYRUSONE STERLING 11 DATA CENTER - PHASE 2: Revision to the approved plan (STMP-2022-0017) showing electrical & telecom duct banks as well as an updated loading dock footprint.
-
CYRUSONE STERLING 11 DATA CENTER PH 2 : REQUEST APPROVAL OF A MODIFIED PROCESS SITE PLAN (STMP) FOR THE CONSTRUCTION OF A DATA CENTER FACILITY WHICH WILL INCLUDE DATA HALLS, OFFICE SPACE, AND ASSOCIATED ROADWAY, PARKING…
-
CYRUSONE STERLING 9 DATA CENTER PH 1B : REQUEST APPROVAL OF A SITE PLAN AMENDMENT (SPAM) TO THE PREVIOUSLY APPROVED STMP-2019-0012 TO MAKE MODIFICATIONS TO THE BUILDING AND INFRASTRUCTURE IN THE PREVIOUSLY APPROVED PH…
-
The applicant requests approval for a minor addition to a principal building on an approved Special Exception pursuant to Section 10.11.01.H.2. for a 14,177-square-foot footprint addition to the existing data center…
-
The county record's description names individuals; see the county record.
-
(Conditional Approval) (STPL) ALLEGRO NORTH CAMPUS - BLDG 2A: Data Center and support facilities.
-
YONDR-TARRING SPEX-2025-0128: A Special Exception to permit a data center use in the General Industry (GI) Zoning District SPEX-2025-0144: A Minor Special Exception to eliminate the berm and fencing requirements along a…
-
Site plan for the construction of 3 Data Center buildings, a warehouse building, and associated infrastructure
-
JK Technology Park #2 - STPL for construction of two (2) data center buildings with associated infrastructure and relocation of pond proposed with future Dulles West Boulevard (designed with CRCP-2020-0012)
-
THE SUBJECT OF THIS APPLICATION CONSISTS OF THE DESIGN OF A 1-STORY DATA CENTER BUILDING AND ASSOCIATED UTILITIES AND INFRASTRUCTURE.
-
(Conditional Approval) JK TECHNOLOGY PARK #3: Proposed Data Center and associated infrastructure (STPL)
Straight-line distance from the school's location (National Center for Education Statistics).
Virginia's 2026 siting law requires a sound study covering schools within 500 feet of a new high-energy
facility before a county can approve it.