Preschool Child Find, 20 Union St NW, Leesburg. Virginia DEQ's records show no data centers within 2 miles, but county records show 28 filings that mention a data center within 2 miles.
28 filings (land-use applications and site plans) that mention a data center, from Loudoun County records; 3 still in county review. Filings come before any DEQ air permit, so some of these may not be on DEQ's records yet.
-
The county record's description names individuals; see the county record.
-
PARAGON PARK III TECH PARK: STPL for two Data Centers building, ROW dedication for right turn lane off Pacific Blvd, parking, SWM/BMP, public water and sanitary sewer lines, and landscaping.
-
NTT VA7 DATA CENTER: SPAM of STMP-2021-0005 to revise Bldg VA7 to the new prototype.
-
DATA CENTERS AT COMPASS CREEK: Site Plan Revision to STPL-2023-0004 (SPAM was not allowed due to SF changes)
-
(Conditional Approval) DULLES BERRY LC8 DATA CENTER: THIS SPAM IS FOR THE REVISION TO CONDITIONALLY APPROVED STMP-2022-0009 LC8 DATA CENTER. REVISIONS INCLUDE MINOR CHANGES TO THE BUILDING FOOTPRINT, GRADING, UTILITIES…
-
The county record's description names individuals; see the county record.
-
Proposed new data center layout and associated infrastructure
-
ARCOLA GROVE REZONING The application is being reviewed under the Revised 1993 Zoning Ordinance. ZMAP-2023-0005: A Zoning Map Amendment to rezone approximately 30 acres to build a Utility Transmission Substation and…
-
DULLES BERRY LC4 DATA CENTER : REQUEST APPROVAL OF A SITE PLAN AMENDEMENT (SPAM), REVISION TO THE THELC4 SITE PLAN TO INCLUDE SECURITY GATE, SECURITY FENCE, MINOR STORM REVISIONS, AND ADDITIONAL DISTURBANCE IN THE…
-
(Conditional Approval) BELMONT LANDBAY KK DATA CENTER : REQUEST APPROVAL OF A SITE PLAN (STPL) FOR THE CONSTRUCTION OF A DATA CENTER, OFFICE, AND ASSOCIATED SITE INFRASTRUCTURE TO SUPPORT THE DEVELOPMENT, IN THE PLANNED…
-
22675 DULLES SUMMIT COURT : REQUEST APPROVAL OF A SITE PLAN (STPL) FOR THE CONSTRUCTION OF TWO HUNDRED SIXTY THOUSAND (260,000) SQUARE FEET DATA CENTER FACILITY, WHICH WILL INCLUDE DATA HALL, OFFICE SPACE, AND…
-
DATA CENTER AT COMPASS CREEK SEC. 4 : REQUEST APPROVAL OF A SITE PLAN (STPL) FOR THE CONSTRUCTION OF THE ADDITION OF TWO BUILDINGS AND ASSOCIATED UTILITIES, IN THE PLANNED DEVELOPMENT INDUSTRIAL PARK (PDIP) ZONING…
-
PARCEL J ASHBURN CENTER : REQUEST APPROVAL OF A MODIFIED PROCESS SITE PLAN (STMP) FOR DEMO OF EXISTING ONE (1) STORY BUILDING AND CONSTRUCTION OF DATA CENTER AND ASSOCIATED INFRASTRUCTURE, IN THE PLANNED DEVELOPMENT -…
-
BELMONT INNOVATION CAMPUS - ZMAP-2022-0021: A Zoning Map Amendment to rezone 84.52 acres from A-3 and PD-GI to PD-IP. SPEX-2022-0042: A Special Exception to increase FAR in the PD-IP zoning district to 1.0.…
-
H5 DATA CENTER : REQUEST APPROVAL OF A SITE PLAN (STMP) FOR A MULTI-STORY DATA CENTER AND ASSOCIATED INFRASTRUCTURE IN THE PD-IP ZONING DISTRICT.
-
TRUE NORTH DATA : REQUEST APPROVAL OF A MODIFIED PROCESS SITE PLAN (STMP) FOR A 309,906 SF DATA CENTER, IN THE PLANNED DEVELOPMENT- OFFICE PARK (PDOP) ZONINING DISTRICT.
-
PROJECT NOVA SOUTHEAST SITE PLAN : REQUEST APPROVAL OF A SITE PLAN (STMP) FOR TWO (2) NEW DATA CENTER FACILITIES WITH ASSOCIATED INFRASTRUCTURE AND BMP IN THE PD-OP ZONING DISTRICT.
-
TECH PARK AT BRAMBLETON : REQUEST APPROVAL OF A SITE PLAN (STMP) FOR FOUR (4) DATA CENTER BUILDINGS AND ON-SITE SUBSTATION IN THE PDIP ZONING DISTRICT
-
VANTAGE VA 3 : REQUEST APPROVAL OF A MODIFIED PROCESS SITE PLAN FOR THE CONSTRUCTIONOF FOUR (4) DATACENTER BUILDINGS TOTALING 2,327,448 SQUARE FEET ALONG WITH THE ASSOCIATED ROAD NETWORK, TWO (2) STREAM CROSSINGS,…
-
DIGITAL LOUDOUN IV-BUILDING S : REQUEST APPROVAL OF A MODIFIED PROCESS SITE PLAN (STMP) FOR CONSTRUCTION OF ONE DATA CENTER BUILDING, GUARD BOOTH BUILDING AND ENTRY PLAZA AREA, AND ASSOCIATED INFRASTRUCTURE AND…
-
INTERGATE ASHBURN DATA CENTER BLDNG A : REQUEST APPROVAL OF A MODIFIED PROCESS SITE PLAN (STMP) FOR A FINAL DATA CENTER AND RELATED INFRASTRUCTURE, DESIGNATED AS BUILDING "A" ON APPROVED APPLICATIONS STPL-2011-0014,…
-
DULLES BERRY LC8 DATA CENTER : REQUEST APPROVAL OF A MODIFIED PROCESS SITE PLAN (STMP) FOR THE CONSTRUCTION OF A 3-STORY DATA CENTER BUILDING AND ASSOCIATED INFRASTRUCTURE, IN THE PLANNED DEVELOPMENT- RESEARCH AND…
-
(Conditional Approval) ARCOLA GROVE DATA CENTERS : REQUEST APPROVAL OF A MODIFIED PROCESS SITE PLAN (STMP) FOR TWO (2) DATA CENTERS AND ASSOICATED INFRASTRUCTURE, IN THE PLANNED DEVELOPMENT- INDUSTRIAL PARK (PDIP)…
-
NTT GLOBAL DATA CENTERS VA8 & VA9 : REQUEST APPROVAL OF A MODIFIED PROCESS SITE PLAN (STMP) FOR THE CONSTRUCTION OF TWO (2) 2-STORY DATA CENTERS, IN THE PLANNED DEVELOPMENT INDUSTRIAL PARK (PDIP) ZONING DISTRICT.
-
DIGITAL LOUDOUN IV PRENTICE DRIVE : REQUEST APPROVAL OF A SITE PLAN AMENDMENT (SPAM) FOR CONTSTRUCITON OF ONE DATA CENTER BUILDING, GUARD BOOTH BUILDING, AND ASSOCIATED INFRASTRUCTURE AND UTILITIES IN THE (PDIP) PLANNED…
-
DULLES BERRY LC4 DATA CENTER : REQUEST APPROVAL OF A MODIFIED SITE PLAN PROCESS (STMP) FOR THE CONSTRUCTION OF A THREE-STORY DATA CENTER BUILDING, IN THE PLANNED DEVELOPMENT - RESEARCH AND DEVELOPMENT PARK (PDRDP)…
-
PROJECT ALLEGRO SOUTH CAMPUS PH 1 : REQUEST APPROVAL OF A MODIFIED PROCESS SITE PLAN (STMP) FOR PHASE 1 OFTHE SOUTH CAMPUS OF A DATA CENTER COMPLEX WITH ASSOCIATED SUPPORT FACILITIES, IN THE (PDIP/R1) PLANNED…
-
ASH 1- BRODERICK DC 2 : REQUEST APPROVAL OF A MODIFIED PROCESS SITE PLAN (STMP) FOR A FINAL SITE PLAN FOR A PROPOSED DATA CENTER USE IN THE PLANNED DEVELOPMENT-INDUSTRIAL PARK (PDIP)
Straight-line distance from the school's location (National Center for Education Statistics).
Virginia's 2026 siting law requires a sound study covering schools within 500 feet of a new high-energy
facility before a county can approve it.